On 6/25/13 3:33 PM, "Daniel Teske" <daniel.teske at digia.com> wrote:

>> Our goal should be to release 5.2 in November, so we have a bit of slack
>> before christmas. Unfortunately we'll also need some time to still do
>> feature development, so the proposal would be to aim for releasing the
>> alpha end of September.
>Shouldn't there be a discussion first on what went wrong with the 5.1
>schedule? 
>Because clearly we are way beyond the end of april target.

Yes, quite a few things took longer then originally anticipated. The
feature freeze did already happen two weeks later then originally planned,
then it took quite some time to get the alpha and beta packages out. In
the end we had a week or two of delays on every stage of the release and
that added up.

>If there's no discussion on why that happend and how we are going to
>improve 
>the process, then this plan will be as unachievable as the last one.

This is something we'll need to discuss. The 5.1 plan was clearly too
optimistic. So we need to go through the problems we had with 5.1 to make
sure we don't repeat them if we want to have a chance to get 5.2 done in
time.

Cheers,
Lars