[Development] Qt 5.12 schedule proposal & proposal for release process change

Edward Welbourne edward.welbourne at qt.io
Tue Apr 17 16:48:08 CEST 2018


Alex Blasche (maanantai 16. huhtikuuta 2018 16.47)
>>> ... I do like to emphasize though that the dates for first beta and
>>> first RC are important (and FF is alpha) because they define times
>>> when certain level of changes are no longer permitted (e.g. after
>>> first beta no API changes). Therefore, you will not get around
>>> setting a target date for first Beta and RC.

Jani Heikkinen (17 April 2018 08:28)
>> - Agree that we should start with the API review immediately.
>> - Beta once API review is done. Lets agree the 'Done' properly to get
>>   it clear for everyone. I already tried to start discussion about it in
>>   http://lists.qt-project.org/pipermail/development/2018-March/032338.html

Edward Welbourne (17 April 2018 11:08)
> As noted in [0], this looks like QUIP material.  Kai proposed, in a
> reply to [0], having a Jira ticket to track the review, with each issue
> it raises being turned into a sub-task of it.  Your Done condition would
> then be the closing of that ticket, which would happen when every API
> review has got a +2, upon which I abandon it.  I'll re-open a review,
> though, if I see any further apparently-material API changes, when I'm
> preparing updates to other reviews.
>
> * [0] http://lists.qt-project.org/pipermail/development/2018-March/032362.html
>
> I don't see anyone volunteering to write that QUIP, so I'll do so when
> time permits, unless someone else speaks up first.

Here's my first attempt at that QUIP:

https://codereview.qt-project.org/226574

	Eddy.