Qt 6.5 status:
-  Branching from '6.5' to '6.5.2' done
- Qt 6.5.2 content is not frozen yet. The target is to freeze the Qt 6.5.2 content later this week
- The target is to release Qt 6.5.2 Wed 28th June

Will we have to pick to 6.5.2 manually or will changes that are currently targeting 6.5 be picked automatically?

Regards,
Arno

For changes that aren’t merged yet, the 6.5.2 branch has to be in the list of pick-to targets (that has been necessary since we branched 6.5.2 off on June 14th), and those cherry-picks have to then be accepted by the release team (as only they can stage changes to that branch).

Changes that have been merged after the branch-off date, but without 6.5.2 as a pick-to target, you can manually cherry-pick. Add Jani or Tarja as a reviewer, and if critical enough, give the respective JIRA ticket (or a new JIRA ticket if that’s what it takes) P0 priority with 6.5.2 as the fix-version.


Volker


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.qt-project.org/pipermail/development/attachments/20230620/bc5a8a77/attachment.htm>


More information about the Development mailing list