[Releasing] FW: [Development] Schedule for Qt 4.8.1
simo.falt at nokia.com
simo.falt at nokia.com
Tue Feb 14 09:52:24 CET 2012
I think it is ok to plan the schedule in dev list. It is affecting to Qt
developers. I would see the releasing list being channel for
practicalities of creating releases.
Simo
On 2/14/12 10:37 AM, "ext Salovaara Akseli" <Akseli.Salovaara at digia.com>
wrote:
>Hi,
>
>Just noticed that conversation about Qt 4.8 release plan \ schedule is
>ongoing on development mailing list.
>How the schedule looks for releasing mailing list participant's point of
>view? Comments, ideas, opinions?
>For me at least preliminary schedule looks promising.
>
>Br,
>Akseli
>
>-----Original Message-----
>From: Turunen Tuukka
>Sent: 14. helmikuuta 2012 8:28
>To: Thiago Macieira; development at qt-project.org
>Subject: Re: [Development] Schedule for Qt 4.8.1
>
>
>
>On 13.2.2012 18.32, "Thiago Macieira" <thiago.macieira at intel.com> wrote:
>
>>On segunda-feira, 13 de fevereiro de 2012 12.28.06, Turunen Tuukka wrote:
>>> Hi All,
>>>
>>> We would like to release next version of Qt Commercial 4.8 around
>>>mid-March.
>>>
>>> It would be really great if we can again sync the LGPL and Commercial
>>> releases both in timing and content to the extent possible.
>>>
>>> If we agree that mid-March is a good target time for the next patch
>>>release,
>>> we should have as much as possible all the fixes in by end of February.
>>> Naturally a patch release will not have any new features, but there are
>>> some fixes that we are very much targeting to be in 4.8.1 such as ones
>>> needed for publishing apps in the Mac App Store.
>>>
>>> Since 4.8 was moved to gerrit, we have been actively redoing our merge
>>> requests, and quite much has already been merged into the 4.8 branch.
>>
>>I think that it's a worthy goal. Let's try to have that release in March
>>then.
>
>
>Excellent. As it is a patch release, I think it will be just fine that
>everybody knows the timing, and can handle the fixes accordingly.
>
>>
>>After that, I'd like to see 4.8 move into a periodic release mode, either
>>in
>>time or in number of changes.
>
>
>For the patch releases there always needs to be the capability to issue
>one quickly in case something urgent comes up (like a serious security
>issue).
>
>Having the patch releases strictly tied into some intervals, or amount of
>fixes does not work well in my opinion. But I do agree that some criteria
>should be agreed upon, so that it is easy to know when the time is right
>for a release.
>
>Then it should also be noted that 4.8 is a bit of a special case as the
>last of the Qt 4 series. It needs a more patch releases than I think will
>be needed for Qt 5 (with regular 6 months for the minor releases it should
>be very easy to migrate between these).
>
>I think good timing for the 4.8 patch releases would the roughly:
>
>4.8.1 in mid-March
>4.8.2 in end-May
>4.8.3 in end-September
>4.8.3 in mid-January 2013
>
>Which leads to about 3 month intervals, that should be suitable for
>increasing the stability of this already mature base.
>
>As said, we need to also see what makes sense content wise, and be
>prepared for a quick release if something urgent comes up.
>
>I am very happy to hear your feedback and thoughts on this. After the
>discussion it would be good to update the wiki with jointly agreed release
>plan for 4.8.
>
>Yours,
>
> Tuukka
>
>_______________________________________________
>Development mailing list
>Development at qt-project.org
>http://lists.qt-project.org/mailman/listinfo/development
>_______________________________________________
>Releasing mailing list
>Releasing at qt-project.org
>http://lists.qt-project.org/mailman/listinfo/releasing