On 2/18/13 16:32 , Tor Arne Vestbø wrote:
> The plan is to merge these initial changes before the freeze on Friday.
And to not worry anyone, I was referring to this schedule, as laid out
by Lars:
> * Friday 22. February: If you have a larger feature/feature branch (not
> yet merged) that you want to have in the release you must have told the
> release team (by mail to releases@) by then.
> * Friday 1. March: Feature branch must be tested new functionality
> documented and ready to integrate.
> * Friday 15. March: Feature freeze. Merge from dev to stable.