Because qt5.2 beta1 was delayed almost a week I think we need to update our release plan as well. So if no-one complains I will update release plan like this:
- Merge from stable to rel: 11th Nov 2013
- String freeze: 11th Nov 2013
- Release Candidate: 19th Nov 2013
- Final Release: 3rd Dec 2013
6th Dec 2013 is public holiday in Finland. That's why I want to plan release as early as possible in that week and of course keep time between RC & final as it was.