[Releasing] Qt 5.14.0 schedule proposal
Edward Welbourne
edward.welbourne at qt.io
Thu May 2 10:24:12 CEST 2019
Jani Heikkinen (2 May 2019 08:00)
> We are in final steps with Qt 5.13.0 release and so on it is time to start planning Qt 5.14.0 initial schedule.
>
> Qt 5.13 isn't indicating anything why we could cut the schedule so my proposal is based on Qt 5.12.0 and Qt 5.13.0 ones:
>
> - 19.08.2019: Soft branching from 'dev' to '5.14' start
> - 26.08.2019: Feature Freeze & Finalize branching from 'dev' to '5.14'
> - 03.09.2019: Alpha release
> - 17.09.2019: Beta1 release
> - 12.11.2019: RC
> - 26.11.2019: Qt 5.14.0 Final Release
>
> And as earlier we will produce additional Beta n releases ~(bi)weekly between beta1 and RC.
>
> Any thoughts?
Only a consistency glitch: that puts FF 13 weeks before final release;
but [0] says we allow 17 weeks. We should either update [0] or do what
it says ! For reference, 17 weeks before 2019-11-26 is 2019-08-30.
* [0] https://wiki.qt.io/Qt5Releasing
Eddy.